Assam: Bhairabi – Sairang railway project progressing towards completion

This project will provide seamless rail connectivity to Mizoram

GUWAHATI-  The Bhairabi-Sairang New Line Railway Project to connect the capital of the North-eastern state of Mizoram to the rest of the country is one such project which is at an advance stage of completion.

The 51.38 Km new line between Bhairabi and Sairang is divided into four sections, namely Bhairabi–Hortoki, Hortoki–Kawnpui, Kawnpui–Mualkhang and Mualkhang–Sairang. Bhairabi – Hortoki section which is of 17.38 km has been completed and commissioned on July, 2024 and train service is operational from August, 2024.

Also Read- 8 coaches of Agartala-Lokmanya Tilak Express derail at Dibalong station

The whole project once completed will be a game changer project in terms of communication and commerce for the people of Mizoram. The economical and environment friendly railway services will have a positive impact on almost all development works in the state.

Construction of the Bhairabi – Sairang railway project involves 48 tunnels in tough terrains. The total length of tunnels in this project is 12853 meters out of which 12807 meters tunneling works has already been completed. The project will have total 55 major bridges and 87 minor bridges.

Also Read- Romance in Sikkim, Visit Yuksom, Lachung, Yumthang Valley, Mount Katao

The work of construction of the tallest pier of the project i.e Pier P – 4 of bridge no. 196 in the approach of Sairang station has also been completed. Height of this pier is 104 meter which is 42 meter taller than the Qutub Minar. The project also includes 5 Road Over Bridges & 6 Road Under Bridges. There will be four stations in this project; Hortoki, Kawnpui, Mualkhang, and Sairang.

Though there are many challenges in execution of this project like very less working season due to very heavy and prolonged monsoons, very tough and hilly terrain through deep forests, poor accessibility, non-availability of construction materials and skilled labor in Mizoram etc., Northeast Frontier Railway is making all efforts for fulfilling its commitment towards early completion of the project.

Also Read- Gurudongmar Lake: The most amazing place in Sikkim

The new rail project will provide enhanced connectivity to the people of the Mizoram, help grow small scale industries in the area and boost tourism of the state.

This project will ensure substantial cost reduction on transportation of passengers and various materials & commodities to this hilly state to cater to the needs of the local population.

Travel time between the capital of Mizoram and nearby places of Assam will reduce significantly. People of the region will get long distance access across the country and uninterrupted supply of essential goods.